OUR PROJECTS
Crusher Control System Upgrade
LOCATION
Pilbara Region, Western Australia
CLIENT
Tier 1 Mining
CONTRACT TYPE
Control Systems Engineering
Installation and Integration of Six New Crushers at Pilbara Mine Site
At X2 Engineering, we pride ourselves on delivering innovative and reliable solutions for challenging projects. Partnering with Linkforce Engineering, our control systems team executed a complex greenfield upgrade within a brownfield process environment by installing six new crushers at a prominent mine site in the Pilbara region of Western Australia.
We designed and implemented a robust control strategy to seamlessly integrate the new crushers, including vendor package interfaces. Our comprehensive engineering solutions addressed the necessary processing changes for the new installations. Rigorous Factory Acceptance Testing (FAT) ensured the system met the highest standards before deployment. The system was successfully commissioned across six shutdown periods, ensuring minimal disruption to operations.
We also provided extensive onsite and offsite support to guarantee a seamless transition and reliable operation of the processing facility.
PROJECT HIGHLIGHTS
- Designed and implemented a custom control strategy for seamless crusher integration.
- Delivered meticulous engineering for all control systems works.
- Conducted thorough Factory Acceptance Testing (FAT) before deployment.
- Successfully commissioned the system across six shutdown periods.
- Provided dedicated onsite and offsite support services.
OUR EXPERTISE
PROUDLY SERVICING THE MINING AND RESOURCES INDUSTRY.